Ohio Valley Connector

BRIEF

Our services included survey, engineering design, routing, meter station design, launcher/receiver design, construction survey and as-builts along 51 miles of proposed pipeline.

For this pipeline project, we provided Equitrans with:

  • survey project management
  • drafting for preliminary survey of approximately 51 miles of pipeline
  • as-built survey
  • drafting alignment sheets
  • GIS file geodatabase.

We also provided:

  • static GPS control survey and adjustment
  • staking of existing and proposed lines
  • preliminary design survey
  • data processing
  • submission to drafting for FERC filing.

In addition, we provided surveying services for the proposed compressor sites, valve sites, access roads, and ancillary sites.

PROJECT DETAILS

Client:
Equitrans, LP

Location:
Ohio and West Virginia

Services
Construction Phase Services
Design
Drafting
FERC
Survey
GIS & Arc GIS Server

SAFETY DETAILS

100%
Project Safety Score
Zero Incidents

Total hours worked: 137 Hours

Total miles driven: 267 Miles

26 Awards Given for On the Spot Safety